NE Krško Reduces Production by 20 Percent Due to Overheated Sava River

Board Member Saša Medaković assures that supply to Croatia and Slovenia is not at risk, but warns of further reductions and a complete shutdown if river temperatures worsen.

Foto: Pham Ngoc Anh na Pexels
Summary
  • NE Krško will reduce production by 20 percent on the night from Wednesday to Thursday as the Sava River temperature approaches the legal limit of 28 degrees.
  • Board member Saša Medaković claims that supply to Croatia and Slovenia is not at risk and that the plant is technically ready to continue operating if authorities grant approval.
  • Unlike Krško, the Paks nuclear plant in Hungary and Cernavodă in Romania physically cannot access water from the Danube due to low water levels.
  • If temperatures worsen, there is a plan for further power reductions and a complete shutdown within five to seven days, but the plant could restart within one day.

The Krško Nuclear Power Plant, which supplies electricity to Croatia and Slovenia, plans to reduce its output by 20 percent on the night from Wednesday to Thursday. The reason is the high temperature of the Sava River, used for cooling the facility, which has approached the legally prescribed environmental limit.

Approaching the Critical Threshold of 28 Degrees

Saša Medaković, a member of the NE Krško management board, explained to HRT that the plant is currently operating safely and stably, but that they are approaching the limit. "When the Sava's inlet temperature at the plant exceeds 25 degrees, combined with our additional heating of three degrees, we reach the 28-degree limit, at which point we are obliged to reduce the plant's output," said Medaković.

He emphasized that the plant is technically and safely capable of operating at higher temperatures, but this requires approval from Slovenian authorities for a temporary relaxation of the discharge water temperature limit. "A prerequisite for this is easing the temperature restriction so we can further heat the Sava at the outlet," he added.

Plan for Further Deterioration

Medaković also revealed a detailed action plan if the heatwave continues. The first phase is a 20 percent power reduction. If that proves insufficient, further reductions will follow. "If the situation continues to worsen, we would reduce power by another 15 percent twice within three to four days. If we reached 50 percent of the plant's capacity, we would not go below that; instead, we would completely shut down the plant within five to seven days," he said.

He stressed that a potential shutdown would not be due to a malfunction but solely an administrative decision. "The plant is completely safe and operational, and it is ready to resume electricity production within one day. There are no other risks," Medaković stated.

Paks and Cernavodă in a Much More Difficult Situation

Comparing the situation with other nuclear power plants in the region, Medaković warned of serious problems in Hungary and Romania. "Unlike us, the Paks and Cernavodă nuclear power plants are in a situation where they physically cannot access water from the Danube," he said. These plants had already requested and received approval in June 2026 to temporarily increase the permitted river heating, but now even that does not help because the Danube's water level is so low that they cannot draw enough cooling water.

"Even when the state needs them, they are unable to deliver electricity," Medaković warned, emphasizing that NE Krško, despite current challenges, remains operational and ready to meet the needs of the power system.

Citizens Need Not Worry

Medaković concluded that there is no need to worry about the security of supply. He noted that nuclear power plants are designed for extreme conditions and that out of about a hundred such facilities in Europe, only a few have had to reduce output during the current and previous heatwaves. "I think we should not worry about this. We have the technical capabilities for production. All decision-makers are aware of this and have mechanisms they can use," he said.

FAQ
Will the reduction in production at NE Krško jeopardize the electricity supply in Croatia? +
According to board member Saša Medaković, the electricity supply in Croatia and Slovenia is not at risk.
Why does NE Krško have to reduce production? +
Due to the high temperature of the Sava River used for cooling. When the water temperature at the plant's inlet exceeds 25 degrees and reaches 28 degrees at the outlet, the plant is obliged to reduce output according to environmental regulations.
Can NE Krško continue operating at full capacity despite the high Sava temperature? +
Technically yes, but it requires approval from Slovenian authorities to temporarily relax the discharge water temperature limit. If the plant is deemed necessary for system stability, it can receive permission to continue operating.
What will happen if the Sava temperature increases further? +
According to the plan, after the initial 20 percent reduction, two additional reductions of 15 percent each would follow within three to four days. If power drops to 50 percent, the plant would be completely shut down within five to seven days.

Log in

You need to log in or register to comment.

Comments (0)
No comments yet. Be the first!
Traži
Popularno
Nedavno pretraživano
helsinški sporazum
liga prvaka
digitalni mediji
Login
Home
Prati nas na Googleu
Categories