Renovation of 'Dragojla' Delayed: Students Again in 'Seljani', Mandić Doubts Contractor

Mayor admitted problems with the pace of works and announced a return to the home school only in the second semester.

Foto: Rui Silva sj na Unsplash
Summary
  • The renovation of Dragojla Jarnević Primary School is delayed, so students will again attend classes at the Braća Seljan School from autumn 2026.
  • Mayor Damir Mandić expressed doubts about the contractor and confirmed a return to the home school only in the second semester.
  • The project worth 9 million euros is financed from EU funds, and after renovation, the school will have new classrooms and switch to single-shift operation.
  • The works were further slowed down by the discovery of a hand grenade during dismantling.

Students of Dragojla Jarnević Primary School will welcome the new school year, starting this autumn, as guests in the premises of the Braća Seljan School. Although it was initially planned that the extensive renovation of the main building would be completed by the start of classes, the works are not progressing at the expected pace.

Mayor Open About Delay

The information was confirmed at a press conference on August 6, 2026, by Mayor Damir Mandić, who emphasized that it is realistic to expect students to return to the renovated 'Dragojla' only during the second semester of the 2026/2027 school year.

"The works on the 'Dragojla' itself are not going at the pace and intensity we expected. We are having certain problems with the contractor. They claim there won't be any problems, but it seems to me they're not telling us everything," Mandić said, as reported by Radio Mrežnica.

Bomb and New Standards

One of the reasons for the slowdown was the unexpected discovery of a hand grenade during the dismantling of the intermediate floor structure on the first floor. As a result, the continuation of the works had to be carried out manually, which further extended the deadlines.

Despite the setback, Mandić emphasized the focus on quality. "The interest is to finish the project as it should be, in the meantime we need to complete the furnishing, and the procurement for that has been completed. In the coming weeks and months, I believe we will be a bit wiser," he added.

School for the 21st Century

Once the works are finally completed, the school will switch to single-shift operation. The project also includes the full utilization of the attic space for new classrooms, the installation of a heating system using heat pumps, and air conditioning for the entire building. The renovated 'Dragojla' will be fully accessible to people with disabilities and reduced mobility.

Financing from EU Funds

The renovation project was contracted for 9,012,981 euros in grant funds. The majority, specifically 8,885,269 euros, is provided by the Recovery and Resilience Facility, while 127,712 euros are allocated from the European Union Solidarity Fund.

FAQ
Where will students of Dragojla Jarnević Primary School attend classes from autumn 2026? +
They will attend classes at the Braća Seljan School, as the renovation of their home school is delayed.
When is the return of students to the renovated 'Dragojla' building expected? +
According to Mayor Mandić, the return is expected in the second semester of the 2026/2027 school year.
What is the total value of the renovation project and from which sources is it financed? +
The project is worth 9,012,981 euros, financed from the Recovery and Resilience Facility (8,885,269 euros) and the EU Solidarity Fund (127,712 euros).
What further slowed down the renovation works? +
During the dismantling of the intermediate floor structure, a hand grenade was found, requiring manual work, which slowed down the process.

Log in

You need to log in or register to comment.

Comments (0)
No comments yet. Be the first!
Traži
Popularno
Nedavno pretraživano
helsinški sporazum
liga prvaka
digitalni mediji
Login
Home
Prati nas na Googleu
Categories