Karlovac: Intersection at Banija Bridge Delayed Until September 4

Unexpected installations in the roadbed have postponed the opening of the access intersection of Banija Street and Obala Trnskog. Work on the bridge itself continues as planned.

Foto: Wikipedia (Raskrižje)
Summary
  • The opening of the intersection of Banija Street and Obala Trnskog has been postponed until September 4, 2026.
  • ECI and gas pipeline installations were found in the roadbed, causing a halt in works.
  • Hrvatski Telekom and E.ON Hrvatska must first carry out interventions on their installations.
  • Works on the Banija Bridge itself continue as planned.

The City of Karlovac has announced that the opening of the access intersection of Banija Street and Obala Trnskog has been postponed until September 4, 2026. The reason is unforeseen circumstances during the rehabilitation works on the Banija Bridge, as reported by Trend Karlovac on Wednesday.

During the works, existing gas pipeline and electronic communications infrastructure (ECI) installations were discovered in the roadbed. As reported by Radio Mrežnica, this caused a halt in the works planned for the bridge rehabilitation.

HT and E.ON Must First Carry Out Interventions

In order for the works to continue, Hrvatski Telekom d.d. and E.ON Hrvatska d.o.o. must first carry out interventions on their installations. After that, the contractor working on the Banija Bridge will be able to resume asphalt paving and rehabilitation of the access intersection.

According to Radio Mrežnica, in an article by Gordan Tomičić, the City emphasizes that HT and E.ON Hrvatska are obliged to first carry out works on their installations in order to continue with the rehabilitation and asphalt paving of the access intersection at the Banija Bridge.

Bridge Works Continue as Planned

Despite the unforeseen situation, works on the bridge itself continue as planned. After that, the rehabilitation of the roadway, asphalt paving, and installation of the transition device will follow, which have been temporarily postponed.

Due to the additional works on existing installations, the opening of the intersection for traffic is planned no later than September 4. The news was published on Wednesday, August 19, 2026.

FAQ
Why was the opening of the intersection at the Banija Bridge postponed? +
Due to the discovery of existing electronic communications infrastructure (ECI) and gas pipeline installations in the roadbed, which caused a halt in the works.
By when is the opening of the intersection of Banija Street and Obala Trnskog expected? +
The opening of the intersection for traffic is planned no later than September 4, 2026.
Who must carry out interventions on the installations before works can resume? +
Hrvatski Telekom d.d. and E.ON Hrvatska d.o.o. must first carry out interventions on their installations.
Have the works on the Banija Bridge itself been halted? +
No, works on the bridge itself continue as planned despite the unforeseen situation with the intersection.

Log in

You need to log in or register to comment.

Comments (0)
No comments yet. Be the first!
Search
Popular
Login
Home
Make 5MIN.hr a preferred source
Follow us on social media
Categories