HAC Tenders Expansion of Zagreb-Karlovac Motorway: €248 Million, Works in 2027

The €248 million tender covers nearly 40 kilometers of motorway and the construction of 36 new structures. Bids will be opened on September 8, and traffic will be maintained with two lanes in each direction during works.

Foto: Wikipedia (Autocesta)
Summary
  • The tender for the construction of the third lane on the Zagreb-Karlovac motorway is worth €248 million, with bids opening on September 8, 2026.
  • Works on the nearly 40-kilometer section, with 36 new structures, are expected to start in 2027 and last 730 working days.
  • The existing Karlovac interchange will be removed and relocated about one kilometer closer to Zagreb, with new interchanges at Stupnik and Ašpergeri also to be built.
  • During construction, traffic will flow without motorway closures, with two lanes in each direction, and a summer ban on works that obstruct traffic.

The project to widen the motorway between Zagreb and Karlovac is entering its decisive phase. Hrvatske autoceste (HAC) has launched a tender with an estimated value of €248 million, and bids from potential contractors will be opened on September 8, 2026. According to current plans, construction work is expected to begin the following year, in 2027.

This is a historic undertaking for Croatian infrastructure, as this section will become the country's first motorway with three lanes in each direction. The need for expansion is clearly evident from traffic data: the Zagreb-Karlovac section carries an average of around 40,000 vehicles daily, while in summer that figure reaches as high as 67,000.

730 Days of Work in Three Shifts

The project covers a section nearly 40 kilometers long, on which as many as 36 new structures will be built, including bridges, viaducts, underpasses, and overpasses. The planned duration of works is 730 working days, and the contractor will be required to work 24 hours a day, in three shifts.

Particularly demanding will be the works on the Kupčina and Kupa-Kupa bridges and the Orlovac viaduct, alongside which entirely new structures will be built. Despite the scale of the works, the motorway will not be closed during construction. Traffic will be maintained at all times with two lanes in each direction, and from June 15 to September 15, no works that would impede the smooth passage of vehicles will be permitted.

New Entrance to Karlovac and Additional Interchanges

For residents of Karlovac and the surrounding area, the key change concerns the existing interchange. It will be completely removed, and the new Karlovac interchange will be built approximately one kilometer closer to Zagreb, at a location between the Orlovac and Drežnik viaducts. This structure will serve as a completely new entrance to the city from the motorway.

In addition, entirely new interchanges at Stupnik and Ašpergeri will be built along the route, the existing Jastrebarsko interchange will be reconstructed, and the construction of an internal Lučko interchange is planned for the needs of Hrvatske autoceste.

FAQ
When will work on the third lane of the Zagreb-Karlovac motorway begin? +
According to plans, work is expected to begin during 2027, after bids are opened on September 8, 2026.
Will the motorway be closed during construction? +
No, the motorway will not be closed. Traffic will be maintained at all times with two lanes in each direction, and during the summer, from June 15 to September 15, works that obstruct traffic will not be permitted.
What happens to the existing Karlovac interchange? +
The existing Karlovac interchange will be completely removed, and a new one will be built about one kilometer closer to Zagreb, between the Orlovac and Drežnik viaducts, serving as the new entrance to the city.
How long will the works last and what is the project value? +
The works are expected to last 730 working days, and the estimated value of the tender for the entire project is €248 million.

Log in

You need to log in or register to comment.

Comments (0)
No comments yet. Be the first!
Search
Popular
Nedavno pretraživano
helsinški sporazum
liga prvaka
digitalni mediji
Login
Home
Prati nas na Googleu
Categories