The estimated cost of the first phase of remediation of illegally dumped waste at the former PPK Velebit site in Gospić has risen to €4.72 million excluding VAT, the Ministry of Environment and Green Transition announced. This represents more than a twofold increase compared to the original estimate of €2.1 million, which the Environmental Protection and Energy Efficiency Fund cited when announcing the first tender in February 2026.
No bids were submitted for that initial call, prompting the Fund to hold additional talks with potential contractors in July 2026. Following these consultations, the value of the works was drastically revised upward. Along with the financial picture, the timeline has also changed: the future contractor will have 12 months to remove the loose waste from the site and another 12 months for its final recovery and disposal. It is worth recalling that the original plan envisaged the entire phase being completed in just six months.
Additional Tender for 650 Tonnes of Bagged Waste
In parallel with the main procedure, the Fund has launched a separate procurement aimed at removing around 650 tonnes of non-hazardous waste stored in big bags. The estimated value of this job is €400,000 excluding VAT. Bids for both tenders will be accepted until the end of August 2026.
The final cost of disposal, the Ministry explains, largely depends on the chemical composition of the waste, with the chlorine content playing a key role. It is precisely this parameter that determines the feasibility and cost of thermal treatment at foreign facilities. The higher the chlorine concentration, the more demanding and financially burdensome the process becomes.
Buried Waste: Still Searching for a Disposal Model
A far greater challenge is posed by the portion of waste that ended up underground. For this, the final remediation model has yet to be selected. In search of a solution, the Fund first contacted 15 foreign operators, after which the inquiry was extended to approximately 60 companies managing hazardous waste landfills or waste-to-energy plants across the European Union. Additionally, inquiries were sent to four addresses regarding the possibility of permanent disposal in abandoned salt mines.
Several preferred options are currently under consideration: disposal at hazardous waste landfills, energy recovery, or a combined approach. The citizens' initiative "Gospić Is Our Home" is expected to receive insight into the proposed remediation models by September 20, 2026. The Ministry emphasizes that this date does not mark the moment of decision-making, but rather the fulfillment of a promise that a proposal will be presented before any public procurement is announced.
Water Is Safe, but Concerns Over Oversight Grow
In the context of safety, the Ministry also addressed the issue of drinking water quality, particularly regarding the potential presence of PFAS compounds. The Croatian Institute of Public Health has confirmed its safety, and an expansion of the groundwater monitoring network has been agreed upon.
The Ministry and the Fund stress that they were never responsible for issuing permits or conducting inspections at that site. This raises the question of why the authorities that had the power to act on the ground failed to notice significant changes in the area between 2020 and 2024. State-led remediation was only initiated when it became clear that the polluter could not bear the costs and that the local level had not responded. The government included the site in the Waste Management Plan in May 2025, giving the Fund the legal basis to act. Preparatory works on the ground began in mid-October 2025, as soon as access to the site was granted after being previously blocked due to criminal proceedings.